Audit: Would cost up to $80M to cancel streetcar, up to $105M to complete it

Minus money spent, completion cost is $68.9M

With a newly released audit in mind that said it could cost up to $80.1 million to cancel the streetcar, and up to $105.7 million to complete it, Cincinnati City Council decided Thursday to continue the construction of the streetcar.